Cleanup is done on a big Kansas oil spill on the Keystone system, the company and EPA say

By John Hanna - Associated Press 2 min read
1 / 2

FILE - In this photo taken by a drone, cleanup continues in the area where the ruptured Keystone pipeline dumped oil into a creek in Washington County, Kan., Dec. 9, 2022. TC Energy, the operator of the Keystone pipline system, has finished cleaning up a massive December 2022 oil spill, and the creek affected by it is flowing naturally again, the company and the U.S. Environmental Protection Agency announced Tuesday, Oct. 31, 2023.

2 / 2

FILE - In this photo taken with a drone, cleanup continues in the area where the ruptured Keystone pipeline dumped oil into a creek in Washington County, Kan., Dec. 9, 2022. TC Energy, the operator of the Keystone pipline system, has finished cleaning up a massive December 2022 oil spill, and the creek affected by it is flowing naturally again, the company and the U.S. Environmental Protection Agency announced Tuesday, Oct. 31, 2023.

TOPEKA, Kan. (AP) 鈥 The operator of the Keystone pipeline system has finished cleaning up a massive December 2022 oil spill, and the creek affected by it is flowing naturally again, the company and the U.S. Environmental Protection Agency say.

Pipeline operator TC Energy promised to continue monitoring the site along Mill Creek in Washington County, about 150 miles (241 kilometers) northwest of Kansas City. The Canada-based company and the EPA鈥檚 regional office announced Tuesday that berms that had diverted the creek around the spill site had been removed.

The EPA said Kansas鈥 environmental agency and the U.S. Army Corps of Engineers also will continue to inspect the area for the next five years or 鈥渦ntil it is determined that monitoring is no longer needed.鈥

The spill dumped nearly 13,000 barrels of crude oil 鈥 each one enough to fill a standard household bathtub 鈥 into the creek as it ran through a rural pasture. The oil was recovered by mid-May, the company has said.

The company said that it has started 鈥渄emobilization鈥 at the site and, 鈥渆xpect to complete these activities by year end.鈥 The pipeline carries oil from Canada to the Texas Gulf Coast.

The company reported in February that a faulty weld in a a pipe bend caused a crack that grew over time under stress. An engineering consultant firm鈥檚 report for U.S. pipeline regulators that became public in May cited pipeline design issues, lapses by its operators and problems caused during pipeline construction as factors in the spill.

The consultants鈥 report said the bend had been 鈥渙verstressed鈥 since its installation in December 2010, likely because construction activity itself altered the land around the pipe. It was the largest onshore spill in nearly nine years.

CUSTOMER LOGIN

If you have an account and are registered for online access, sign in with your email address and password below.

NEW CUSTOMERS/UNREGISTERED ACCOUNTS

Never been a subscriber and want to subscribe, click the Subscribe button below.

Starting at $4.79/week.